Sample photoRM-D0867 · Infrastructure
Drilling, construction and mechanization of 15no boreholes (7 with hand pumps and 8 mechanized)
In progressLater than plannedChecked 30 Oct 2026Level 1 of 4: Reported by the ministry
What's happening: Imported from the District Assembly register. Awaiting GCO review.
Sample photoProgress
District Assembly project register, Bono East Region
30 October 2026SourceNext: Not yet reported
Files and sources
- District Assembly project register, Bono East RegionSource · 30 October 2026