Tumu to Sissili to Navrongo road
In progressNext check-in: 23 November 2026Checked 1 May 2026Level 2 of 4: Confirmed on site with dated photos
Sample photoProgress
Up from 13.76% in February 2026. Includes bridges over the Kanyibie River (36 m) and Bechelihu (24 m).
- Site visitGhana News Agency, August 2026
Next: Not yet reported
Progress over time
3 dated progress points on record
May 2026Aug 2026
Files and sources
Where next
More results in Big Push
- Wa to Han road rehabilitationRM-B25In progress
- Tumu to Han to Lawra road upgrade, km 0 to 10RM-B23In progress
- Accra to Kumasi Expressway, six lanesRM-B37Starting soon
More results in Sissala East Municipal
- Construction of 1No. 3-Unit Classroom Block with 4-Seater KVIP Toilet, 2-unit Urinal, 3No. Teachers Tables and Chairs and Extension of Electricity to Facility at Kulfuo-FiriwaRM-D3052Delivered
- Completion of 1No. 3-Unit Classroom Block with 4-Seater KVIP Toilet, 2-unit Urinal, 3No. Teachers Tables and Chairs and Extension of Electricity to Facility at Sumboru(LEGACY PROJECT)RM-D3053Delivered
- Construction of 1No. 3-Unit Classroom Block with 4-Seater KVIP Toilet, 2-unit Urinal, 3No. Teachers Tables and Chairs and Extension of Electricity to Facility at BakwallaRM-D3051Delivered