Sample photoRM-D0844 · Infrastructure
Construction of chips compound at akropong
In progressLater than plannedChecked 30 Oct 2026Level 1 of 4: Reported by the ministry
What's happening: Imported from the District Assembly register. Awaiting GCO review.
Sample photoProgress
District Assembly project register, Bono East Region
30 October 2026SourceNext: Not yet reported
Files and sources
- District Assembly project register, Bono East RegionSource · 30 October 2026
Where next
More results in Nkoranza South Municipal
- Construction of 1No. 3-unit classroom block with ancillary facilities at okatakyie JHS-breman, nkoranzaRM-D0839Delivered
- Construction of 1 No. 2 unit classroom block with ancillary facility at mim-amponsakrom.RM-D0840Delivered
- Construction of a 24 hour economy market at nkoranza in the nkoranza south districtRM-D0847In progress