Sample photoRM-D0262 · Infrastructure
Construction of 1 No. 6-unit classroom block at afasiebon
In progressLater than plannedChecked 28 Oct 2026Level 1 of 4: Reported by the ministry
What's happening: Imported from the District Assembly register. Awaiting GCO review.
Sample photoProgress
District Assembly project register, Ashanti Region
28 October 2026SourceNext: Not yet reported
Files and sources
- District Assembly project register, Ashanti RegionSource · 28 October 2026
Where next
More results in Atwima Kwanwoma
- Drilling and mechanization of 8 No. boreholes at adumasa, twedie(TVET), twedie(immigration), foase (education office), foase (health office), ampatia, kokoben & nweneso No.3RM-D0259Delivered
- Construction of 12-seater w/c toilet with a mechanized borehole at akosomoRM-D0260Delivered