Sample photoRM-D0145 · Infrastructure
Drilling and mechanization of 1No. borehole with fire hydrant at jacobu
DeliveredChecked 28 Oct 2026Level 1 of 4: Reported by the ministry
What's happening: Imported from the District Assembly register. Awaiting GCO review.
Sample photoProgress
District Assembly project register, Ashanti Region
28 October 2026SourceDelivered
Files and sources
- District Assembly project register, Ashanti RegionSource · 28 October 2026
Where next
More results in Amansie Central
- Drilling and mechanisation of 5No. boreholes with reinforced concrete reservoir stand and overhead tankRM-D0155In progress
- Drilling and mechanisation of 5No. boreholes with reinforced concrete reservoir stand and overhead tankRM-D0156In progress
- Renovation of old court to health center and ambulance service centerRM-D0160In progress